Figure 16
6. Click Finish.
Decommissioning old servers
Decommissioning the old servers requires three steps. Be sure you follow these steps in sequential
order.
1. Moving key roles and services
2. Moving existing connectors
3. Uninstalling old servers
If the server was a Domain Controller and held any of the following roles, it moved to the new server
before you can decommission the old servers:
Domain Naming Master
Schema Master
RID Master
Infrastructure Master
PDC Emulator
Global Catalog
To move these roles and services:
1. Make the new server the Domain Naming Master.
a. Right-click Active Directory Domains and Trusts, as shown in Figure 17, and select
Operations Master.
20